Road closures round here in numbers

Every road closure booked on the councils' and utilities' records round Saffron Walden, Thaxted, Great Dunmow and Haverhill since July 2020, when the Department for Transport's Street Manager started. Worked out Mon 23 Nov 18:51.

Over the years

Still loading: we're reading Street Manager's records for 2022 to 2025 tonight, so those years are short until it's done.

Year by year

YearRoad closuresCancelledTypical length (days)A week or moreEmergenciesSets of traffic lights
2026 (so far)3,54528%3.017%3923,131
20255921%2.024%6131
20240–––03
202320%31.050%02
202279030%4.030%7941
20212,46534%3.021%1104,274
2020 (from July)85723%4.028%431,750

Road closures that went ahead (or are still booked) by the year they start; cancelled is the share of those booked that never happened; a typical closure is the median booked length. 2020 counts from July, when Street Manager started.

In detail: in 2023

4road closures went aheadof 4 booked
0%of booked closures were cancelled0 never happened
4different roads closedat least once
31.0 daysa typical closure50% booked for a week or more

Closures a month

Jan: 1 closuresJan1Feb: 0 closuresFebMar: 0 closuresMarApr: 1 closuresAprMay: 1 closuresMayJun: 0 closuresJunJul: 1 closuresJulAug: 0 closuresAugSep: 0 closuresSepOct: 0 closuresOctNov: 0 closuresNovDec: 0 closuresDec0

Closures that went ahead (or are still booked), by the month they start. Temporary traffic lights are counted apart: 3 sets in 2023.

The numbers as a table
MonthClosures
Jan 20231
Feb 20230
Mar 20230
Apr 20231
May 20231
Jun 20230
Jul 20231
Aug 20230
Sep 20230
Oct 20230
Nov 20230
Dec 20230

Booked, and what happened

  • 0% were cancelled. 0 of 4 booked closures never happened, so a closure on the records isn't certain until it starts. We say when a closure is marked as started.
  • 25% were extended after they were booked (1 closures), usually by about 271 days.
  • 0% finished more than a day early (0 of the 1 marked as finished).
  • 0 were emergencies: burst pipes, gas leaks and the like, closed with no notice.

How long they last

  1. Under a day1
  2. 1 to 3 days0
  3. 3 days to a week1
  4. 1 to 4 weeks0
  5. Over 4 weeks2

Who closes the roads

  1. Cadent Gas1
  2. Cambridgeshire County Council1
  3. UK Power Networks Eastern & London1
  4. Essex County Council1

By the organisation doing the work. The councils' own count includes road repairs, resurfacing and improvements.

Why

  1. Gas1
  2. Road repairs and resurfacing1
  3. Electricity1
  4. Road improvements1

The roads closed most often

  1. Hadham Road, Bishop's Stortford1
  2. Coronation Street, Cambridge1
  3. Howards Lane, Horseheath1
  4. School Lane, Newport1

Each closure booked on the road counts once, however long it lasted.

By council

  1. Cambridgeshire County Council2
  2. Hertfordshire County Council1
  3. Essex County Council1

How we count

A closure is any works or activity whose traffic management is a road closure, counted by its booked start. Street Manager replaced the old system (EToN) in July 2020; its monthly archive has every record since, and we've read it live since 17 November 2026. Cancelled means Street Manager says so. Extended means its booked end moved later after it was first booked. Finished early compares when it was marked as stopped with its booked end. We don't count overruns: works are often marked as stopped days after they really end, so the records can't tell an overrun from late paperwork. Type of works is worked out from who's doing them (a water company, a broadband firm…) and what Street Manager calls them. National Highways' own closures feed (motorways and trunk roads) isn't in these numbers yet: the National Highways works counted here are the ones they record in Street Manager. Contains public sector information licensed under the Open Government Licence v3.0.