Road closures round here in numbers
Every road closure booked on the councils' and utilities' records round Saffron Walden, Thaxted, Great Dunmow and Haverhill since July 2020, when the Department for Transport's Street Manager started. Worked out Mon 23 Nov 18:51.
Over the years
Still loading: we're reading Street Manager's records for 2022 to 2025 tonight, so those years are short until it's done.
The numbers as a table
Year by year
| Year | Road closures | Cancelled | Typical length (days) | A week or more | Emergencies | Sets of traffic lights |
|---|---|---|---|---|---|---|
| 2026 (so far) | 3,545 | 28% | 3.0 | 17% | 392 | 3,131 |
| 2025 | 59 | 21% | 2.0 | 24% | 6 | 131 |
| 2024 | 0 | – | – | – | 0 | 3 |
| 2023 | 2 | 0% | 31.0 | 50% | 0 | 2 |
| 2022 | 790 | 30% | 4.0 | 30% | 7 | 941 |
| 2021 | 2,465 | 34% | 3.0 | 21% | 110 | 4,274 |
| 2020 (from July) | 857 | 23% | 4.0 | 28% | 43 | 1,750 |
Road closures that went ahead (or are still booked) by the year they start; cancelled is the share of those booked that never happened; a typical closure is the median booked length. 2020 counts from July, when Street Manager started.
In detail: since July 2020
Booked, and what happened
- 30% were cancelled. 3,520 of 11,718 booked closures never happened, so a closure on the records isn't certain until it starts. We say when a closure is marked as started.
- 9% were extended after they were booked (748 closures), usually by about 4 days.
- 22% finished more than a day early (1,083 of the 4,817 marked as finished).
- 565 were emergencies: burst pipes, gas leaks and the like, closed with no notice.
How long they last
- Under a day1,925
- 1 to 3 days2,380
- 3 days to a week2,134
- 1 to 4 weeks1,399
- Over 4 weeks360
Who closes the roads
- BT1,232
- Cambridgeshire County Council1,183
- Essex County Council1,156
- Anglian Water814
- Affinity Water809
- Hertfordshire County Council554
- Suffolk County Council548
- UK Power Networks Eastern & London466
- Gigaclear386
- Cambridge Water Company382
By the organisation doing the work. The councils' own count includes road repairs, resurfacing and improvements.
Why
- Water2,047
- Road repairs and resurfacing1,819
- Phone and broadband1,817
- Road improvements1,472
- Electricity490
- Gas226
- Railway157
- An event91
The roads closed most often
- Hadham Road, Bishop's Stortford25
- Mill End Green Road, Great Easton23
- Birchanger Lane, Birchanger23
- Great Canfield Road, Great Canfield23
- Station Road, Great Shelford23
- Bumpstead Road, Hempstead21
- Wethersfield Road, Sible Hedingham21
- Bishops Stortford Bypass, Bishop's Stortford21
- Burton End, Haverhill20
- Radwinter Road, Ashdon20
- Duck Street, Little Easton20
- Holders Green Road, Lindsell20
Each closure booked on the road counts once, however long it lasted.
By council
- Essex County Council3,948
- Cambridgeshire County Council2,344
- Suffolk County Council1,033
- Hertfordshire County Council861
- National Highways12
How we count
A closure is any works or activity whose traffic management is a road closure, counted by its booked start. Street Manager replaced the old system (EToN) in July 2020; its monthly archive has every record since, and we've read it live since 17 November 2026. Street Manager started in July 2020, so works booked before then aren't counted. Cancelled means Street Manager says so. Extended means its booked end moved later after it was first booked. Finished early compares when it was marked as stopped with its booked end. We don't count overruns: works are often marked as stopped days after they really end, so the records can't tell an overrun from late paperwork. Type of works is worked out from who's doing them (a water company, a broadband firm…) and what Street Manager calls them. National Highways' own closures feed (motorways and trunk roads) isn't in these numbers yet: the National Highways works counted here are the ones they record in Street Manager. Contains public sector information licensed under the Open Government Licence v3.0.